Awani International
  • LIVE
  • Videos
  • US-China
  • BRICS-RT
  • ASEAN
  • West Asia
  • Shows
  • Podcast
  • BM
    EN
  • LIVE
  • Login
  • BM
    EN
  • LIVE
  • Login
Awani International
  • LIVE
  • Videos
  • US-China
  • BRICS-RT
  • ASEAN
  • West Asia
  • Shows
  • Podcast
Several reported killed in Iran protests over economic hardships
Russian air defences down 29 Moscow-bound drones over 20 hours, mayor says
Yemen’s Aden airport shuts as Saudi-UAE rift deepens
  • PRIVACY POLICY
  • TERMS OF USE
  • ADVERTISE WITH US
  • INVESTOR

Astro AWANI | Copyright © 2025 Measat Broadcast Network Systems Sdn Bhd 199201008561 (240064-A)

New Zealand pylon collapses after too many bolts removed

Bernama
Bernama
24/06/2024
05:32 MYT
New Zealand pylon collapses after too many bolts removed
Transpower chief executive Alison Andrew stated that a crew from Omexom was undertaking routine maintenance on the base plates, which secure the tower to the ground, when the pylon collapsed. - aran Marsh-Goudie/via AP
WELLINGTON: A power pylon in New Zealand collapsed and caused power outage to thousands after workers removed too many bolts, the German news agency (dpa) reported on Monday, quoting the country's transmission provider.
The incident, which occurred north of Auckland on June 20, resulted in power cut to about 100,000 properties in the Northland region of northern New Zealand. Full power was restored only on Sunday.
Transpower chief executive Alison Andrew stated that a crew from Omexom was undertaking routine maintenance on the base plates, which secure the tower to the ground, when the pylon collapsed.
"All the nuts securing the tower to the base plate on three legs have been removed, which has caused the tower to lift off the base plate and fall," she said in a statement.
"It is unprecedented and inconceivable that so many nuts were removed at once."
A full investigation had been launched, she said.
"While we are very grateful that no one was hurt when the tower fell, the failure to follow procedure resulted in a significant power outage that had a real impact on the people of Northland," she added.
"We are committed to learning from this event and implementing any additional controls that may be identified."
Omexom's managing director Mornez Green commented that the incident was unprecedented.
The workers involved had been stood down pending the investigation, he said.
"I can assure you we will be open and transparent in the investigation."