Irregularities in Boustead's RM9 billion combat ship project: What you need to know

Melissa Fernando 30/11/2020 | 10:45 MYT
The government has already paid RM6 billion for the first ship to be delivered in April 2019 but not one ship has been built to date. BERNAMA file pic
KUALA LUMPUR:WHAT'S GOING ON?


Patriot’s president Brigadier General (Rtd) Datuk Mohamed Arshad Raji said the six vessels were sorely needed to boost Malaysia’s defences against naval threats as well as economic necessity. Image via Sinar Harian


WHAT IS CAUSING THE DELAY?
WHY IT MATTERS?

WHAT'S NEXT?
  1. Appointment of Naval Group France as a rescue contractor to complete at least two LCS units.
  2. Completion of at least two units by BNS with the remaining contract ceiling.
  3. Termination of the contract with BNS.
BHIC said forensic audit findings, commissioned in February 2020, were handed over to the MACC in September. Upon completion of of the audit last Saturday, BHIC lodged a report with MACC for investigations to probe possible irregularities in the LCS project.