MRT phase 2 is almost 95 per cent completed

Bernama
December 13, 2016 06:10 MYT
The 30 km Phase Two involves 19 stations between Semantan to Kajang and part of the RM23 billion MRT project which spans 51 kms with 31 stations. - Photo Rapid KL
Progress-wise, the second and final phase of the Mass Rapid Transit (MRT) project involving the Semantan-Kajang line is almost 95 per cent completed.
MRT Sungai Buloh-Kajang (MRT SBK) project director, Marcus Karakashian said progress includes all station structure works, rail systems and trains.
"We expect the MRT test run for the Phase Two to take place as early as January 2017 before its operation in July the same year," he told a media briefing here on Tuesday.
The 30 km Phase Two involves 19 stations between Semantan to Kajang and part of the RM23 billion MRT project which spans 51 kms with 31 stations.
Meanwhile, Feeder Bus and Infrastructure Development chief Rudyanto Azhar said 112 feeder buses would begin operating on 25 routes from the 12 stations for the phase one, Sungai Buloh-Semantan line this Friday.
He said the buses would run on a frequency of between 10 minutes and 15 minutes with the routes designed to serve residential and commercial areas within 3 km of an MRT station. -- Bernama