Awani International
  • LIVE
  • Videos
  • US-China
  • BRICS-RT
  • ASEAN
  • West Asia
  • Shows
  • Podcast
  • BM
    EN
  • LIVE
  • Login
  • BM
    EN
  • LIVE
  • Login
Awani International
  • LIVE
  • Videos
  • US-China
  • BRICS-RT
  • ASEAN
  • West Asia
  • Shows
  • Podcast
Europe won't be 'blackmailed' by Trump tariffs, says Danish PM
Trump tells Norway he no longer feels obligation to think only of peace
Japan PM Takaichi calls Feb 8 election seeking mandate for spending plans, defence build-up
  • PRIVACY POLICY
  • TERMS OF USE
  • ADVERTISE WITH US
  • INVESTOR

Astro AWANI | Copyright © 2025 Measat Broadcast Network Systems Sdn Bhd 199201008561 (240064-A)

Phase One of Putrajaya MRT line still undergoing rectification

Bernama
Bernama
21/01/2022
03:47 MYT
Phase One of Putrajaya MRT line still undergoing rectification
The MRT Putrajaya Line (formerly known as the Sungai Buloh-Serdang-Putrajaya Line) runs through 56.2 kilometres and has 36 stations for Phases One and Two, starting from the Kwasa Damansara station to Putrajaya. - BERNAMA
KUALA LUMPUR: The Mass Rapid Transit (MRT) Putrajaya Phase One line is still undergoing some rectification by the turnkey operator in preparation for full operations, said MRT Corporation Sdn Bhd.
On Nov 16, 2021, MRT Corp chief executive officer Datuk Mohd Zarif Hashim said the line may be ready for revenue service in the second quarter (Q2) of 2022.
Prior to the announcement, MRT Corp had postponed the opening date for MRT Putrajaya Line Phase One from August to mid-November 2021.
The trial operations for Phase One has been ongoing since April 29, 2021.
A total of 16 trains have been running between Kwasa Damansara MRT Station and Kampung Batu MRT Station in full-service mode -- minus the passengers -- to stimulate actual operations.
The MRT Putrajaya Line (formerly known as the Sungai Buloh-Serdang-Putrajaya Line) runs through 56.2 kilometres and has 36 stations for Phases One and Two, starting from the Kwasa Damansara station to Putrajaya.
"Meanwhile, the construction of the MRT Putrajaya Line Phase Two is also progressing well," MRT Corp told Bernama via email.
As of Oct 4, 2021, the construction of Phase Two line is 93.52 per cent completed, and it is expected to begin operations in January 2023.
-- BERNAMA