Second Penang Bridge project to remain within budget, JKSB
Bernama
October 17, 2013 17:19 MYT
October 17, 2013 17:19 MYT
The Second Penang Bridge project cost remains within the RM4.5 billion budget, despite several safety testings, says the bridge concessionaire, Jambatan Kedua Sdn Bhd (JKSB).
Its managing director Datuk Ir Dr Ismail Mohamed Taib said previously there was a savings of RM50 million, which is now being used for safety management, quality requirement as well as landscaping.
"The project cost is still within the RM4.5 billion budget," he told reporters after a load testing at the cable stayed bridge of the project today.
Ismail said the Second Penang Bridge was 99% complete and the JKSB expects it to be fully ready by Nov 8.
The opening date will be announced upon approval from the Works Ministry.
According to Ismail, the remaining work on the bridge involves the expansion joints, minor and final touches, which are likely to be completed by the end of this month.
Once done, he said the JKSB will send a report to be endorsed by the Department of Occupational Safety and Health (DOSH) and the Penang Municipal Council (MPPP), before the bridge is opened to the public.
The Second Penang Bridge covers 24 km with 16.9km over water, and links Batu Maung on the island to Batu Kawan on the mainland.